Tuesday, April 30, 2024

FG approves N3bn Sukuk funds for Numan-Jalingo Road project

Uba Group

Alhaji Muazu Sambo, Minister of State for Works and Housing, says there is a provision of N3billion Sukuk fund in 2022 by the Federal Government to finance the Numan- Jalingo Road in Adamawa and Taraba states.

Sambo announced this on Saturday during an inspection of federal road projects within Taraba and Adamawa states.

He gave the assurance that once the Sukuk fund was accessed, there would be remarkable progress at the construction site.

“The 103 kilometre Numan-Jalingo Road is part of the Maiduguri –Calabar Highway.

“The section of the road that is not motorable is not acceptable for the road is the only connection between the North and South on the North Eastern axis of the country,” Sambo said.

The minister added that he wouldn’t blame the contractor for the slow pace of work.

According to him, it was the insufficient budgetary provision in the past and COVID-19 pandemic that affected the progress of work.

He said that with improved funding, the contractor was expected to service its equipment and be more serious on the construction work.

If the company was found not to have the capacity to complete the job, government would not hesitate to terminate the contract and re-award it to a competent one, he said.

While briefing the Minister on the progress of work on the Numan- Jalingo Road, a Senior Civil Engineer at the site, Maria Zirrah, representing the Federal Controller of Works, said that insecurity, lack of construction materials and funding were responsible for the slow pace of work on the project.

Also, the Project Engineer of Deux Project Limited, handling the Numan-Jalingo project, Frank Koshihuk, said that inflation, poor funding and insecurity were the major challenges besetting the construction work.

The Numan-Jalingo Road rehabilitation was awarded to Deux Project Nigeria Limited at the cost of N11.6billion in March 2017 for completion in July 2019.

NAN reports that the Federal Government released N1.5billion to the contractor who executed seven per cent of the work so far.

(NAN).

Popular Articles